Basic Features
The distribution of the reactor core and associated control and
safety systems is follows these design criteria:
- Upwards cooling flow.
- Free access of reactor personnel to the top of pool with the
reactor operating at full power.
- Easy access to the reactor core from the top of pool.
- Control and safety rods drives are located below the reactor
tank.
- The reactor shut down system consists of two different and
independent systems: the reactor control and safety plates and
a gadolinium injection system.
- Cooling of the core during shutdown is by natural circulation
of the pool water through the core.
- Water injection system to protect against LOCA
consequences.
Key Project Data
The contract for the construction of the reactor was signed in
september, 1992, and work began in March, 1993. During 1993, the
basic design of the plant systems, and on advancing in the structural
design and calculus of the civil works and reactor pool tank in
order to allow construction works to proceed. Overall progress
during that year reached 7%.
The detail engineering of the plant systems began in 1994. At
the site, ground-movement operations were initiated early that
year, followed by the beginning of civil construction works in
June. By February, manufacture of the reactor and auxiliary pools
began in an Egyptian workshop. Overall progress by the end of
the year reached 27%.
Work continued at a good pace during 1995 on the civil works,
the building being specially prepared to allow the late entry
of the reactor and auxiliary pools.
Prototypes were assembled at INVAP
laboratories to test safety systems and parts of the instrumentation
and control complex. In December, the reactor pool was placed
in its final position. Overall progress by the end of the year
reached 51%.
In 1996, the reactor block and surrounding structures were built.
Operations started on several simultaneous mounting fronts, namely:
piping, electric power system cabling, instrumentation & control
system cabling, and ventilation ducts. System integration tests
and an overall pre-delivery verification were carried out at INVAP
laboratories on the reactor operation console, reactor protection
system and supervision and control systems. Overall progress by
the end of the year reached 80%.
The reactor and auxiliary pool inner structures were assembled
between March and July 1997. Operations began by April on the
assembly of the control room and I&C electronic systems. Final
tests for releasing the assembly and erection of the plant systems
were carried out in August.
Formal commissioning began in September 1997.
At a first stage, tests were carried out without loading nuclear
fuel. Integration tests were run to check the operation of the
plant systems and I&C complex.
Fuel was loaded in the core on November 24th, and first criticality
was reached on November 27th. Core neutron parameters were measured
(reactivity, power distribution) at the end of the year.
The power operation stage was initiated in February 1998, and
the reactor's rated power (22 MW) was reached on March 11th.
A preliminary acceptance certificate was obtained for the plant
on March 18th 1998.
|